Facilities Projects Home | Anschutz Medical Campus Development Program | Active Projects | Completed Projects

9th Ave Campus Remediation and Property Transfer

project manager

Ken Neeper 303-724-0749

project architect

Walsh Environmental Engineers and Scientists

general contractor

PCL Construction

gross square footage

2,500,000

project cost

$17 million

project completion

January 2011

project overview

UCD will perform remediation activities on approximately 2.5 million gross square feet of buildings, prior to the sale and transfer of the buildings to Shea Properties for re-development. The remediation work includes asbestos abatement and removal of all environmentally sensitive items such as polychlorinated biphenyl's (PCBs), chlorofluorocarbons (CFC's), underground fuel storage tanks, mercury containing light bulbs and switches, etc, as required by environmental regulations, prior to demolition.

 

 