project manager
Ken Neeper 303-724-0749
Mike Vigil 303-724-1141
project architect
Various
general contractor
Various
total square footage
Various
project cost
$6.6 million
project completion
Summer/Fall 2007
project overview
Phase 10 Infrastructure development includes the following:
Building Demolition - Demolition of US Army buildings 220, 226, 632 and 633 to clear space for infrastructure routing, building development, parking and removal of hazardous structures.
Water and Storm Sewer - Installation of water and storm lines in Victor Street.
Telecommunications Duct bank - New duct bank in 17th Avenue as well as west of the Fitzsimons Commons.
Sanitary Sewer - New sanitary sewer lines in 17th Ave.